An Industrial Guidance Bureau (IGB) set up at present in the Directorate of Industries and Commerce is functioning for effective coordination between the line departments to enable the entrepreneurs to get various licenses. Weekly meetings are conducted to facilitate easy clearances.
To simplify the procedures and regulations, timelines are fixed for each department such that Licences / clearances are issued by the concerned department strictly within the specified period as mentioned below Common Application received through IGB is forwarded within 3 days to the line departments for the following purposes.
Apply online https://msmeonline1.py.gov.in/msmeonline/
SI. No | Line Departments | Purpose | |
---|---|---|---|
1 | Chief Inspectorate of Factories and Boilers | CIF | Clearance under Factories Act |
2 | Directorate of Science, Technology and Environment | DSTE | Environment / Pollution Clearance |
3 | Town and Country Planning | TCP | Site clearance |
4 | Puducherry Planning Authority | PPA | Clearance for building plan approval |
5 | Town & Country Planning Department – Land Use Conversion Committee | LCC | Land use Conversion |
6 | Revenue Department | REV | Clearance from land acquisition |
7 | Municipality/Commune Panchayat | LB | Public objection / issue of permission |
Sr. No. | Enclosures | CIF | DSTE | TCP | PPA | REV | LB | IGB |
---|---|---|---|---|---|---|---|---|
1 | Common Application | 1 | 1 | 1 | 1 | 1 | 1 | 1 |
2 | Acknowledgement Part I / Part II & NOC for enhancement / modification | 1 | 1 | 1 | 1 | 1 | 1 | 1 |
3 | Attested copy of Land Document / Lease Deed | 1 | - | 1 | 1 | 1 | 1 | 1 |
4 | Site & Building Plan (Blue Print) | 4 | 1 | 2 | 1 | 1 | 1 | 1 |
5 | Process details with flow chart & Pollution details | 1 | 1 | - | - | - | 1 | 1 |
6 | Partnership Deed / Memorandum of Articles | 1 | - | - | - | - | 1 | 1 |
7 | Resolution for authorization | 1 | - | - | - | - | 1 | 1 |
8 | Building Plan Approval | - | - | 1 | 1 | - | 1 | 1 |
9 | Electricity Demand Bill | - | - | - | - | - | 1 | 1 |
10 | Form 1C & Chalan | 1 | - | - | - | - | - | 1 |
11 | FMB Sketch (Vacant Land) | - | - | 1 | - | 1 | - | 1 |
Sl.No | Item/Activity | Department/ Organisation | Time limit/ (working days) |
---|---|---|---|
Pre Establishment Stage | |||
1 | Forwarding of common application to the concerned Departments | District Industries Centre | 3 |
2 | Issue of NOC and Consent to establish | Pondicherry Pollution Control Committee | 30 |
3 | Site clearance | Town and Country Planning Department | 30 |
4 | Approval of factory building and machinery lay-out | Inspectorate of Factories and Boilers | 30 |
5 | Permission for land-use conversion/ground water clearance (outside the industrial estate) | Town and Country Planning Department / Agriculture Department | 30 |
6 | Clearance under Revenue Acts (if required) | Revenue Department | 30 |
7 | Licence,(if required) | Food and Drugs Administration | 30 |
8 | Statutory permission for establishment of the unit | Municipality/ Commune Panchayat | 30 |
Post Establishment Stage | |||
9 | Licence | Municipality / Commune Panchayat | 30 |
10 | Factory Licence | Inspectorate of Factories | 30 |
11 | Air and Water Consent for operation of the unit | Pondicherry Pollution Control Committee | 30 |